Your views and suggestions
2 public submissions were received, 7 reports received from internal departments within Kildare County Council, 3 reports/comments from Prescribed Bodies
The submissions have been evaluated and a report was compiled by the Chief Executive for the Athy MD Elected Members of Kildare County Council.
Outcomes
The above Part 8 was approved by the members of the Athy Municipal District, at their meeting on 15th July 2024.
It was agreed by all the members that the Part 8 for the above proposed development at Skenagun Castledermot, Athy Co Kildare be approved subject to modifications outlined below:
1. The proposed development shall be carried out in accordance with the plans and particulars placed on public display on 3rd April 2024, except where altered or amended by the following modifications.
2. The proposed development shall be occupied by persons who comply with Local Need Criteria as set out in Table 3.4 of the Kildare County Development Plan 2023-2029. The dwelling(s) when completed shall be first occupied for a minimum period of ten years as a sole place of permanent residence by the intended occupants. Details of the intended occupants local need compliance shall be submitted to the Planning Authority for written agreement prior to the commencement of development.
3. The proposed development shall not impair existing land or road drainage.
4. Finishes shall be in accordance with the drawings submitted and details of finishes including doors, rainwater goods and window frames shall be agreed in writing with the planning office prior to their installation.
5. Boundary treatments shall be agreed in writing with the Planning Authority prior to their installation.
6. Final details regarding the requirements of the Council’s Environment Department, as identified in their submissions and responded to by the Housing Department in its report on submissions, (included as Appendix 2 of this Report), shall be agreed prior to commencement of development.
7. Final details regarding the requirements of Uisce Éireann and the Water Services Department as set out in their report and responded to by the Housing Department in its report on submissions, (included as Appendix 2 of this Report), shall be agreed prior to commencement of development.
8. Final details regarding the details of design and traffic management of the works, pavement materials, roads, vehicular access footpaths, parking and cycle spaces, public lighting etc as raised by the Transportation Department in their Reports and responded to by the Housing Department in its report on submissions and included as Appendix 2 of this Report shall be agreed prior to commencement of development.
9. A Stage 2 and Stage 3 Roads Safety Audit shall be carried out by an independent approved and certified Auditor on the completed works as raised by the Transportation Department in their Reports and responded to by the Housing Department in its report on submissions and included as Appendix 2 of this Report shall be agreed prior to commencement of development.
10. An Acoustic Noise Assessment will be carried out in accordance with Building Regulation requirements.
11. Final details regarding a root management plan and landscaping shall be agreed with Transportation Department to ensure that landscaping and roots do not interfere and damage shared surfaces, prior to commencement of development.
12. A Construction Management Plan should be submitted before the works commence.
13. Site development works shall be confined to the hours of 07:00 to 18:00 Monday to Friday and 08:00 to 14:00 on Saturdays. No site development works shall take place outside of these hours, or on Sundays or Public Holidays. Any alteration to these times shall be subject to the prior written consent of the Planning Authority.